Considering-1000 ft both vertical and horizontal pipe line
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Plumber a) Plumber | 0.5 | day | 700 | per day | 700 | 350 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator b) Plumber Helper | 0.5 | day | 550 | per day | 550 | 275 | |
| 3 | Hire charge for air pressure pump c)Hire charge for air pressure pump | 0.5 | day | 500 | per day | 500 | 250 | |
| 4 | d) Sundries, T & P etc. | LS | 145 | |||||
| Sub-Total | 1020 | |||||||
| Contractor's Profit | 10% | 0.1 | 102 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 35.7 | |||||
| Total | 1157.7 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 93.87 | ||||
| Grand Total | 1251.57 | |||||||
| Rate per rft | 1.25 | |||||||
| Rate per rm | 4.1 | |||||||