32.110 Cleaning and removing inside rust from existing old GI pipe of different dia meter etc. All completed as per direction of Engineer- in charge.

Considering-1000 ft both vertical and horizontal pipe line

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Plumber a) Plumber 0.5 day 700 per day 700 350
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator b) Plumber Helper 0.5 day 550 per day 550 275
3 Hire charge for air pressure pump c)Hire charge for air pressure pump 0.5 day 500 per day 500 250
4 d) Sundries, T & P etc. LS 145
Sub-Total 1020
Contractor's Profit 10% 0.1 102
Contractor's Overhead Expenses 3.5% 0.035 35.7
Total 1157.7
Add VAT with adjustment factor. 1.08108 7.5% 0.075 93.87
Grand Total 1251.57
Rate per rft 1.25
Rate per rm 4.1