Breakup

32.112 Taking out unserviceable old MS collapsible gate and refitting after minor repair (excluding cost of material) etc. All completed as per direction of Engineer- in charge.

Considering 1 No. MS collapsible gate

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 1 day 600 per day 600 600
2 Ordinary labour Ordinary labour 1 day 550 per day 550 550
3 Mason / Mosaic mistry Mason 0.5 day 700 per day 700 350
5 Concrete for slab (1:2:4) Cement concrete works (1:2:4) 0.015 cum 20355.5 % cft 7246.56 108.7
4 Cutting clamp, removing screws, welding machine, T & P, & sundries etc LS 500
Sub-Total 2108.7
Contractor's Profit 10% 0.1 210.87
Contractor's Overhead Expenses 3.5% 0.035 73.8
Total 2393.37
Add VAT with adjustment factor. 1.08108 7.5% 0.075 194.06
Grand Total 2587.43
Rate per each 2587
Rate per each 2587