Considering 1 No. MS collapsible gate
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 1 | day | 600 | per day | 600 | 600 | |
| 2 | Ordinary labour Ordinary labour | 1 | day | 550 | per day | 550 | 550 | |
| 3 | Mason / Mosaic mistry Mason | 0.5 | day | 700 | per day | 700 | 350 | |
| 5 | Concrete for slab (1:2:4) Cement concrete works (1:2:4) | 0.015 | cum | 20355.5 | % cft | 7246.56 | 108.7 | |
| 4 | Cutting clamp, removing screws, welding machine, T & P, & sundries etc | LS | 500 | |||||
| Sub-Total | 2108.7 | |||||||
| Contractor's Profit | 10% | 0.1 | 210.87 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 73.8 | |||||
| Total | 2393.37 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 194.06 | ||||
| Grand Total | 2587.43 | |||||||
| Rate per each | 2587 | |||||||
| Rate per each | 2587 | |||||||