32.115 Sanitary blockage removal of Basin, Sink, waste water down pipe etc. All completed as per direction of Engineer- in charge.

Considering 1 No. Job

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sweeper for ODD JOB Sweeper for odd job 0.1 day 800 per use 800 80
2 T & P, & sundries etc LS 50
Sub-Total 130
Contractor's Profit 10% 0.1 13
Contractor's Overhead Expenses 3.5% 0.035 4.55
Total 147.55
Add VAT with adjustment factor. 1.08108 7.5% 0.075 11.96
Grand Total 159.51
Rate per each 160