Breakup

32.118 Taking out old unserviceable Aluminium Door/window frame and shutter etc. All completed as per direction of Engineer- in charge.

Considering 1 No. Aluminium Door/window

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.15 day 600 per day 600 90
2 Ordinary labour Ordinary labour 0.15 day 550 per day 550 82.5
3 Cutting clamp, removing screws, T & P, & sundries etc LS 27.5
Sub-Total 200
Contractor's Profit 10% 0.1 20
Contractor's Overhead Expenses 3.5% 0.035 7
Total 227
Add VAT with adjustment factor. 1.08108 7.5% 0.075 18.41
Grand Total 245.41
Rate per each 245
Rate per each 245