Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement | 1.87 | bags | 410 | per bag | 410 | 766.7 | |
| 2 | Sand (F.M. 1.2) Sand (F.M. 1.2) | 7.03 | cft | 1900 | per % cft | 19 | 133.57 | |
| 3 | White Cement White cement | 3.6 | kg | 27 | per kg | 27 | 97.2 | |
| 4 | Head mason / Mosaic head mistry Head mason | 1 | nos | 800 | per day | 800 | 800 | |
| 5 | Mason / Mosaic mistry Mason | 2 | nos | 700 | per day | 700 | 1400 | |
| 6 | Skilled labour Skilled labour | 2 | nos | 600 | per day | 600 | 1200 | |
| 7 | Ordinary labour Ordinary labour | 3 | nos | 550 | per day | 550 | 1650 | |
| 8 | Ordinary labour Local carriage, sundries, T & P & washing of sand etc. | 1 | LS | 550 | per day | 550 | 550 | |
| 9 | Scaffolding Additional scaffolding work | 1 | LS | 10 | per sft | 400 | 400 | |
| 10 | Roof tiles of size 100 mm x200 mm or equivalent (Red colour) (country made) Roof tiles of size 100 mm x 200 mm (Red colour) Considering 100 sft of work Cost of roof tiles | 100 | sft | 14690 | per % sft | 146.9 | 14690 | |
| 11 | Roof tiles of size 100 mm x200 mm or equivalent (Red colour) (country made) Add wastage | 100 | sft | 14690 | per % sft | 7.34 | 734 | |
| Sub-Total | 22421.47 | |||||||
| Contractor's Profit | 10% | 0.1 | 2242.15 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 784.75 | |||||
| Total | 25448.37 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2063.38 | ||||
| Grand Total | 27511.75 | |||||||
| Rate per sft | 275.12 | |||||||
| Rate per sqm | 2961.39 | |||||||