06.20.1 18 mm thick marble stone flooring In ground floor

Considering 100 ( 10'-0" x 10'-0") sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 18 mm thick marble stone, Indian standard quality (Bansowara/ Indian grey/ Indian pink or equivalent) (a)Cost of materials : 18 mm thick marble stone 100 sft 460 per sft 460 46000
2 White Cement White cement 4 kg 27 per kg 27 108
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Grey cement for sand cement mortar base & slury 3.64 bag 410 per bag 410 1492.4
4 Sand (F.M. 1.2) Sand (F.M. 1.2) 4.16 cft 1900 per % cft 19 79.04
5 Sand (F.M. 2.2) Sand (F.M. 2.2) 4.16 cft 5380 per % cft 53.8 223.81
6 Hire charge of marble cutting and shaping machine including cutting disc. (b)Cost for cutting, shaping, tools and plants etc. : Hire charge of cutting and shaping machine in/c cutting disc. 1 day 550 per day 550 550
7 Foreman/Supervisor Foreman 1 no 850 per day 850 850
8 Machine operator Machine operator 1 no 700 per day 700 700
9 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 1 no 550 per day 550 550
10 Mason / Mosaic mistry (c)Labour cost for laying : Mason 5.5 nos 700 per day 700 3850
11 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 2 nos 550 per day 550 1100
12 Hire charge of marble polishing machine including polishing stone (d)Polishing : Hire charge of marble polishing machine in/c polishing stone 2.5 days 620 per day 620 1550
13 Machine operator Operator 2.5 nos 700 per day 700 1750
14 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 2.5 nos 550 per day 550 1375
Sub-Total 60178.25
Contractor's Profit 10% 0.1 6017.83
Contractor's Overhead Expenses 3.5% 0.035 2106.24
Total 68302.32
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5538.02
Grand Total 73840.34
Rate per sft 738.4
Rate per sqm 7948.14