Breakup

06.24.1 18 mm thick marble stone

Considering, 12 X 3'-2" = 38.04 rft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Head mason / Mosaic head mistry A) Labour cost for moulding: Head Mason 2 nos 800 per day 800 1600
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 2 nos 550 per day 550 1100
3 Hire charge of marble cutting disk B) Cost of Materials and Equipment: Hire charge of marble cutting disk 1 no 450 per day 450 450
4 Water Proofing Paper (12 Size) Water Proofing Paper (12 Size) 8 no 22 each 22 176
5 Water Proofing Paper (320 Size) Water Proofing Paper (320 Size) 8 no 24 each 24 192
6 Hire charge of electric grinding machine Hire charge of Electric grinding Machine 2 days 260 per day 260 520
7 Acid stone Acid stone 1 no 450 each 450 450
Sub-Total 4488
Contractor's Profit 10% 0.1 448.8
Contractor's Overhead Expenses 3.5% 0.035 157.08
Total 5093.88
Add VAT with adjustment factor. 1.08108 7.5% 0.075 413.02
Grand Total 5506.9
Rate per rft 144.77
Rate per rm 474.99