Considering, 12 X 3'-2" = 38.04 rft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Head mason / Mosaic head mistry A) Labour cost for moulding: Head Mason | 2 | nos | 800 | per day | 800 | 1600 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 2 | nos | 550 | per day | 550 | 1100 | |
| 3 | Hire charge of marble cutting disk B) Cost of Materials and Equipment: Hire charge of marble cutting disk | 1 | no | 450 | per day | 450 | 450 | |
| 4 | Water Proofing Paper (12 Size) Water Proofing Paper (12 Size) | 7 | nos | 22 | each | 22 | 154 | |
| 5 | Water Proofing Paper (320 Size) Water Proofing Paper (320 Size) | 7 | nos | 24 | each | 24 | 168 | |
| 6 | Hire charge of electric grinding machine Hire charge of Electric grinding Machine | 2 | days | 260 | per day | 260 | 520 | |
| 7 | Acid stone Acid stone | 1 | no | 450 | each | 450 | 450 | |
| Sub-Total | 4442 | |||||||
| Contractor's Profit | 10% | 0.1 | 444.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 155.47 | |||||
| Total | 5041.67 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 408.78 | ||||
| Grand Total | 5450.45 | |||||||
| Rate per rft | 143.27 | |||||||
| Rate per rm | 470.07 | |||||||