Breakup

06.24.2 16 mm thick marble stone

Considering, 12 X 3'-2" = 38.04 rft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Head mason / Mosaic head mistry A) Labour cost for moulding: Head Mason 2 nos 800 per day 800 1600
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 2 nos 550 per day 550 1100
3 Hire charge of marble cutting disk B) Cost of Materials and Equipment: Hire charge of marble cutting disk 1 no 450 per day 450 450
4 Water Proofing Paper (12 Size) Water Proofing Paper (12 Size) 7 nos 22 each 22 154
5 Water Proofing Paper (320 Size) Water Proofing Paper (320 Size) 7 nos 24 each 24 168
6 Hire charge of electric grinding machine Hire charge of Electric grinding Machine 2 days 260 per day 260 520
7 Acid stone Acid stone 1 no 450 each 450 450
Sub-Total 4442
Contractor's Profit 10% 0.1 444.2
Contractor's Overhead Expenses 3.5% 0.035 155.47
Total 5041.67
Add VAT with adjustment factor. 1.08108 7.5% 0.075 408.78
Grand Total 5450.45
Rate per rft 143.27
Rate per rm 470.07