Considering, 12 X 3'-2" = 38.04 rft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Head mason / Mosaic head mistry A) Labour cost for moulding: Head Mason | 1.5 | nos | 800 | per day | 800 | 1200 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 1.5 | nos | 550 | per day | 550 | 825 | |
| 3 | Hire charge of marble cutting disk B) Cost of Materials and Equipment: Hire charge of marble cutting disk | 1 | no | 450 | per day | 450 | 450 | |
| 4 | Water Proofing Paper (12 Size) Water Proofing Paper (12 Size) | 6 | nos | 22 | each | 22 | 132 | |
| 5 | Water Proofing Paper (320 Size) Water Proofing Paper (320 Size) | 8 | nos | 24 | each | 24 | 192 | |
| 6 | Hire charge of electric grinding machine Hire charge of Electric grinding Machine | 2 | days | 260 | per day | 260 | 520 | |
| 7 | Acid stone Acid stone | 1 | no | 450 | each | 450 | 450 | |
| Sub-Total | 3769 | |||||||
| Contractor's Profit | 10% | 0.1 | 376.9 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 131.92 | |||||
| Total | 4277.82 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 346.85 | ||||
| Grand Total | 4624.67 | |||||||
| Rate per rft | 121.58 | |||||||
| Rate per rm | 398.9 | |||||||