Breakup

06.24.3 12 mm thick marble stone

Considering, 12 X 3'-2" = 38.04 rft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Head mason / Mosaic head mistry A) Labour cost for moulding: Head Mason 1.5 nos 800 per day 800 1200
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 1.5 nos 550 per day 550 825
3 Hire charge of marble cutting disk B) Cost of Materials and Equipment: Hire charge of marble cutting disk 1 no 450 per day 450 450
4 Water Proofing Paper (12 Size) Water Proofing Paper (12 Size) 6 nos 22 each 22 132
5 Water Proofing Paper (320 Size) Water Proofing Paper (320 Size) 8 nos 24 each 24 192
6 Hire charge of electric grinding machine Hire charge of Electric grinding Machine 2 days 260 per day 260 520
7 Acid stone Acid stone 1 no 450 each 450 450
Sub-Total 3769
Contractor's Profit 10% 0.1 376.9
Contractor's Overhead Expenses 3.5% 0.035 131.92
Total 4277.82
Add VAT with adjustment factor. 1.08108 7.5% 0.075 346.85
Grand Total 4624.67
Rate per rft 121.58
Rate per rm 398.9