Breakup

06.27 Supplying and setting 12 mm thick Indian or equivalent granite stone of approved quality complying accepted National/ International standards, texture and size on wall with 12 mm thick cement sand (50% F.M. 1.2 and 50% F.M 2.2) mortar (1:2) including cutting and grinding the granite stone slab, setting in position keeping horizontal and vertical alignment correct, filling the joints with white cement, cutting and grinding the top surface, finishing etc including water, electricity and other charges complete in all respect and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 12 mm thick granite stone(Indian/equivalent) A) Cost of materials : 12 mm thick marble stone 100 sft 400 per sft 400 40000
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Grey cement 1.7 bag 410 per bag 410 697
3 Sand (F.M. 1.2) Sand (F.M. 1.2) 2.08 cft 1900 per % cft 19 39.52
4 Sand (F.M. 2.2) Sand (F.M. 2.2) 2.08 cft 5380 per % cft 53.8 111.9
5 White Cement White cement 4 kg 27 per kg 27 108
6 Hire charge of marble cutting and shaping machine including cutting disc. B) Cost for cutting, shaping, tools and plants etc. : Hire charge of cutting and shaping machine in/c cutting disc. 1 day 550 per day 550 550
7 Foreman/Supervisor Foreman 1 no 850 per day 850 850
8 Machine operator Machine operator 1 no 700 per day 700 700
9 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 1 no 550 per day 550 550
10 Mason / Mosaic mistry C) Labour cost for laying : Mason 5.5 nos 700 per day 700 3850
11 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 2 nos 550 per day 550 1100
12 Scaffolding Scaffolding 100 sft 10 per sft 10 1000
13 Hire charge of marble polishing machine including polishing stone D) Polishing : Hire charge of marble polishing machine in/c polishing stone 2.5 days 620 per day 620 1550
14 Machine operator Machine operator 2.5 nos 700 per day 700 1750
15 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 2.5 nos 550 per day 550 1375
Sub-Total 54231.42
Contractor's Profit 10% 0.1 5423.14
Contractor's Overhead Expenses 3.5% 0.035 1898.1
Total 61552.66
Add VAT with adjustment factor. 1.08108 7.5% 0.075 4990.75
Grand Total 66543.41
Rate per sft 665.43
Rate per sqm 7162.69