06.31 Added rate for each additional floor above ground floor for tiles works

considering test no 1

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Add for each addl. floor above ground floor 1 - 550 per day 14.53 14.53
Sub-Total 14.53
Contractor's Profit 10% 0.1 1.45
Contractor's Overhead Expenses 3.5% 0.035 0.51
Total 16.49
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1.34
Grand Total 17.83
Rate per test 18
Rate per test 18