Breakup

07.1.1 Individual & combined footing, pile cap, raft/mat, floor slab and foundation beam up to plinth level

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-3) 1 18275 18275 18275
1 Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-1) 1 1657.916666 cft per day 1657.92 1657.92
1 Materials (From Secondary Input : Item B-3) 1 18275 18275 18275
1 Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-1) 1 1657.916666 cft per day 1657.92 1657.92
Sub-Total 39865.84
Contractor's Profit 10% 0.1 3986.58
Contractor's Overhead Expenses 3.5% 0.035 1395.3
Total 45247.72
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3668.73
Grand Total 48916.45
Rate per cft 489.16
Rate per cum 17274.69
Help