Breakup

07.1.2 Pedestal, column, column capital, lift wall and wall up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-3) 1 18275 18275 18275
1 Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-3) 1 2486.875 cft per day 2486.88 2486.88
Sub-Total 20761.88
Contractor's Profit 10% 0.1 2076.19
Contractor's Overhead Expenses 3.5% 0.035 726.67
Total 23564.74
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1910.65
Grand Total 25475.39
Rate per cft 254.75
Rate per cum 8996.5