Breakup

07.1.3 Floor / roof slab, T-beam, L-beam and rectangular beam, tie beam, lintel, stair case slab and step etc. up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-3) 1 18275 18275 18275
1 Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-2) 1 1989.5 cft per day 1989.5 1989.5
Sub-Total 20264.5
Contractor's Profit 10% 0.1 2026.45
Contractor's Overhead Expenses 3.5% 0.035 709.26
Total 23000.21
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1864.88
Grand Total 24865.09
Rate per cft 248.65
Rate per cum 8781.07
Help