Breakup

07.1.4 Cornice, railing, drop wall, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-3) 1 18275 18275 18275
1 Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-4) 1 3315.833333 cft per day 3315.83 3315.83
Sub-Total 21590.83
Contractor's Profit 10% 0.1 2159.08
Contractor's Overhead Expenses 3.5% 0.035 755.68
Total 24505.59
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1986.94
Grand Total 26492.53
Rate per cft 264.93
Rate per cum 9356
Help