Breakup

07.2.1 Individual & combined footing, pile cap, raft/mat, floor slab and foundation beam up to plinth level

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-4) 1 29466.5 29466.5 29466.5
1 Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-1) 1 1657.916666 cft per day 1657.92 1657.92
Sub-Total 31124.42
Contractor's Profit 10% 0.1 3112.44
Contractor's Overhead Expenses 3.5% 0.035 1089.35
Total 35326.21
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2864.28
Grand Total 38190.49
Rate per cft 381.9
Rate per cum 13486.8
Help