Breakup

07.2.2 Pedestals, column, column capital, lift wall and RCC wall up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-4) 1 29466.5 29466.5 29466.5
1 Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-2) 1 1989.5 cft per day 1989.5 1989.5
Sub-Total 31456
Contractor's Profit 10% 0.1 3145.6
Contractor's Overhead Expenses 3.5% 0.035 1100.96
Total 35702.56
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2894.8
Grand Total 38597.36
Rate per cft 385.97
Rate per cum 13630.53
Help