07.2.3 Floor / roof slab, T-beam, L-beam and rectangular beam, tie beam, lintel, stair case slab and steps etc. up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-4) 1 29466.5 29466.5 29466.5
1 Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-1) 1 1657.916666 cft per day 1657.92 1657.92
Sub-Total 31124.42
Contractor's Profit 10% 0.1 3112.44
Contractor's Overhead Expenses 3.5% 0.035 1089.35
Total 35326.21
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2864.28
Grand Total 38190.49
Rate per cft 381.9
Rate per cum 13486.8