Breakup

07.2.4 Cornice, railing, drop wall, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-4) 1 29466.5 29466.5 29466.5
1 Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-3) 1 2486.875 cft per day 2486.88 2486.88
Sub-Total 31953.38
Contractor's Profit 10% 0.1 3195.34
Contractor's Overhead Expenses 3.5% 0.035 1118.37
Total 36267.09
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2940.57
Grand Total 39207.66
Rate per cft 392.08
Rate per cum 13846.31
Help