Breakup

07.3.3 Floor / roof slab, T-beam, L-beam and rectangular beam, tie beam, lintel, stair case slab and steps etc. upto ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-5) 1 30248.5 30248.5 30248.5
1 Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-2) 1 1989.5 cft per day 1989.5 1989.5
Sub-Total 32238
Contractor's Profit 10% 0.1 3223.8
Contractor's Overhead Expenses 3.5% 0.035 1128.33
Total 36590.13
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2966.76
Grand Total 39556.89
Rate per cft 395.57
Rate per cum 13969.55
Help