Breakup

07.4.1 Individual & combined footing, pile cap, raft/mat, floor slab and foundation beam up to plinth level

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-6) 1 30945 30945 30945
1 Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-1) 1 1657.916666 cft per day 1657.92 1657.92
Sub-Total 32602.92
Contractor's Profit 10% 0.1 3260.29
Contractor's Overhead Expenses 3.5% 0.035 1141.1
Total 37004.31
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3000.35
Grand Total 40004.66
Rate per cft 400.05
Rate per cum 14127.77