Breakup

07.4.3 Floor / roof slab, T-beam, L-beam and rectangular beam, tie beam, lintel, stair case slab and steps etc. up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-6) 1 30945 30945 30945
1 Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-2) 1 1989.5 cft per day 1989.5 1989.5
Sub-Total 32934.5
Contractor's Profit 10% 0.1 3293.45
Contractor's Overhead Expenses 3.5% 0.035 1152.71
Total 37380.66
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3030.86
Grand Total 40411.52
Rate per cft 404.12
Rate per cum 14271.5
Help