Breakup

07.4.4 Cornice, railing, drop wall, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-6) 1 30945 30945 30945
1 Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-4) 1 3315.833333 cft per day 3315.83 3315.83
Sub-Total 34260.83
Contractor's Profit 10% 0.1 3426.08
Contractor's Overhead Expenses 3.5% 0.035 1199.13
Total 38886.04
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3152.92
Grand Total 42038.96
Rate per cft 420.39
Rate per cum 14846.07