Breakup

07.5.1 Individual & combined footing, pile cap, raft/mat and foundation beam up to plinth level

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-7) 1 32057 32057 32057
1 Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) (From Secondary Input : Item A-1) 1 1657.916666 cft per day 1657.92 1657.92
Sub-Total 33714.92
Contractor's Profit 10% 0.1 3371.49
Contractor's Overhead Expenses 3.5% 0.035 1180.02
Total 38266.43
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3102.68
Grand Total 41369.11
Rate per cft 413.69
Rate per cum 14609.46