Breakup

07.5.2 Pedestal, column, column capital, lift wall and RCC wall upto ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-7) 1 32057 32057 32057
1 Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-2) 1 1989.5 cft per day 1989.5 1989.5
Sub-Total 34046.5
Contractor's Profit 10% 0.1 3404.65
Contractor's Overhead Expenses 3.5% 0.035 1191.63
Total 38642.78
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3133.2
Grand Total 41775.98
Rate per cft 417.76
Rate per cum 14753.19
Help