Breakup

07.6.1 For column, wall, beam, slab, drop wall, cornice etc. up to ground floor

Considering 100 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials (From Secondary Input : Item B-8) 1 36093.5 36093.5 36093.5
1 Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-4) 1 3315.833333 cft per day 3315.83 3315.83
Sub-Total 39409.33
Contractor's Profit 10% 0.1 3940.93
Contractor's Overhead Expenses 3.5% 0.035 1379.33
Total 44729.59
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3626.72
Grand Total 48356.31
Rate per cft 483.56
Rate per cum 17076.92