Considering 100 cft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Materials (From Secondary Input : Item B-8) | 1 | 36093.5 | 36093.5 | 36093.5 | |||
| 1 | Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day)(From Secondary Input : Item A-4) | 1 | 3315.833333 | cft per day | 3315.83 | 3315.83 | ||
| Sub-Total | 39409.33 | |||||||
| Contractor's Profit | 10% | 0.1 | 3940.93 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1379.33 | |||||
| Total | 44729.59 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3626.72 | ||||
| Grand Total | 48356.31 | |||||||
| Rate per cft | 483.56 | |||||||
| Rate per cum | 17076.92 | |||||||