Breakup

07.10 Added rate for RCC works/fair-faced concrete works (materials, consumables and laying/placing concrete) in column, column capital, lift wall & wall, T- beam, L-beam, rectangular beams, floor / roof slab, cantilever slab, waffle slab and drop panels where the free height of the structure exceeds 4 meter (rate is considered for each additional meter height)

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Head mason / Mosaic head mistry Extra head mason 0.1 no 800 per day 800 80
1 Mason / Mosaic mistry Extra mason 0.2 no 700 per day 700 140
1 Skilled labour Extra skilled labour 0.2 no 600 per day 600 120
1 Ordinary labour Extra ordinary labour 1 no 550 per day 550 550
1 Ordinary labour Extra for local carriage, storage & sundries etc. 1 LS 550 per day 33 33
Sub-Total 923
Contractor's Profit 10% 0.1 92.3
Contractor's Overhead Expenses 3.5% 0.035 32.3
Total 1047.6
Add VAT with adjustment factor. 1.08108 7.5% 0.075 84.94
Grand Total 1132.54
Rate per cft 1133
Rate per cum 40011.89