Considering 01 no of test
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Laboratory technician ( diploma in engg in relevant field having minimum 3yrs exp) Lab Technician | 0.33 | no. | 1400 | per day | 1400 | 462 | |
| 2 | Assistant laboratory technician Assistant Lab Technician | 0.33 | no. | 850 | per day | 850 | 280.5 | |
| Sub-Total | 742.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 74.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 25.99 | |||||
| Total | 842.74 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 68.33 | ||||
| Grand Total | 911.07 | |||||||
| Rate per test | 911 | |||||||
| Rate per per test | 911 | |||||||