Construction of sanitary latrine (4' X 4') for labourers in the construction site
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 36 " dia RCC ring for latrine and soak well Cost of materials : a) 36 " dia RCC ring- 5 for latrine and 5 for soak well | 10 | nos | 300 | each | 300 | 3000 | |
| 2 | 36" dia RCC Slab for soak well cover b) 36" dia RCC Slab for soak well cover | 1 | nos | 300 | each | 300 | 300 | |
| 3 | 36" dia RCC Slab with ceramic long pan and sanitary seal c) 36" dia RCC Slab with ceramic long pan and sanitary seal | 1 | nos | 950 | each | 950 | 950 | |
| 4 | 3" dia RCC post 12'-0" long d) 3" dia RCC post 12'-0" long | 4 | nos | 950 | each | 950 | 3800 | |
| 5 | 0.45mm couragated sheet walling & roofing e) 0.45mm couragated sheet walling & roofing | 132 | sft | 30 | per sft | 30 | 3960 | |
| 6 | Jarul f) wood | 1.25 | cft | 1800 | per cft | 1800 | 2250 | |
| 9 | Carpenter Carpenter | 1 | no | 700 | per day | 700 | 700 | |
| 10 | Mason / Mosaic mistry Mason | 1 | no | 700 | per day | 700 | 700 | |
| 11 | Ordinary labour Ordinary labour | 6 | nos | 550 | per day | 550 | 3300 | |
| 7 | g) 1.5" dia pvc pipe (6' high) for gas ventilation, 0.75" UPVC water supply pipe line, 1 no plastic bib cock with necessary elbow, socket etc, 4" dia PVC pipe for connecting two pits, 1 no plastic bodna etc. | LS | 1000 | |||||
| 8 | h) Removal of latrine & soak well, back fill pits with sand, levelling, dressing etc. (less salvage value) | LS | 2000 | |||||
| 12 | Tools and plant, nail, washer etc. | LS | 229.17 | |||||
| Sub-Total | 22189.17 | |||||||
| Contractor's Profit | 10% | 0.1 | 2218.92 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 776.62 | |||||
| Total | 25184.71 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2042 | ||||
| Grand Total | 27226.71 | |||||||
| Rate per each | 27227 | |||||||
| Rate per each | 27227 | |||||||