Breakup

01.21 Supply and placing of waste bin (separate waste bins for organic, inorganic and hazardaous wastes) with necessary manpower support for proper disposal of wastes daily at the recommended place or city corporation/municipality damping ground area nearest to site. All complete as per direction of engineer in charge.

For each construction site

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Waste bin made of plastic material Cost of materials : a) Bins (Plastic material) 3 nos 1250 each 1250 3750
2 Polythine Bag etc LS 500
Sub-Total 4250
Contractor's Profit 10% 0.1 425
Contractor's Overhead Expenses 3.5% 0.035 148.75
Total 4823.75
Add VAT with adjustment factor. 1.08108 7.5% 0.075 391.11
Grand Total 5214.86
Rate per site 5215
Rate per site 5215