Considering 1 liter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Water reducing admixture in concrete: Type - A Cost of admixture | 1 | liter | 150 | per litre | 150 | 150 | |
| 1 | Ordinary labour Carriage, safe storage, mixing & sundries etc. | 1 | LS | 550 | per day | 16.5 | 16.5 | |
| Sub-Total | 166.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 16.65 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 5.83 | |||||
| Total | 188.98 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 15.32 | ||||
| Grand Total | 204.3 | |||||||
| Rate per liter | 204 | |||||||
| Rate per liter | 204 | |||||||