Considering 10 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Primer for laying PVC membrane on wall Cost of primer on the surface to be bonded | 1 | liter | 580 | per litre | 580 | 580 | |
| 1 | Water-proofing PVC membrane Cost of membrane in/c 10% wastage and laping | 11 | sqm | 610 | per sqm | 610 | 6710 | |
| 1 | Foreman/Supervisor Cost for laying membrance in/c cleaning surface : Foreman | 0.5 | no | 850 | per day | 850 | 425 | |
| 1 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 1 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 1 | Ordinary labour Local carriage, storage, tools & plant, sundries etc. | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 8840 | |||||||
| Contractor's Profit | 10% | 0.1 | 884 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 309.4 | |||||
| Total | 10033.4 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 813.52 | ||||
| Grand Total | 10846.92 | |||||||
| Rate per sqm | 1084.7 | |||||||
| Rate per sqm | 1084.7 | |||||||