Considering 10 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Primer for laying PVC membrane on wall Cost of membrane in/c 15% wastage and laping | 11.5 | sqm | 580 | per litre | 580 | 6670 | |
| 1 | Foreman/Supervisor Cost for laying membrance in/c cleaning surface : Foreman | 0.25 | no | 850 | per day | 850 | 212.5 | |
| 1 | Skilled labour Skilled labour | 0.25 | no | 600 | per day | 600 | 150 | |
| 1 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 1 | Ordinary labour Local carriage, storage, tools & plant, sundries etc. | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 7582.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 758.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 265.39 | |||||
| Total | 8606.14 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 697.79 | ||||
| Grand Total | 9303.93 | |||||||
| Rate per sqm | 930.4 | |||||||
| Rate per sqm | 930.4 | |||||||