Considering 1000 kg of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 M.S. rod: 300 grade. in/c splice & wastage | 1010 | kg | 65000 | per M. ton | 65 | 65650 | |
| 2 | G.I. wire G.I. Wire | 10 | kg | 120 | per kg | 120 | 1200 | |
| 3 | Rod binder Rod binder | 2 | no | 700 | per day | 700 | 1400 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to rod binder | 9 | no | 550 | per day | 550 | 4950 | |
| 5 | Ordinary labour Local carriage, T & P etc. | 1 | LS | 550 | per day | 1100 | 1100 | |
| Sub-Total | 74300 | |||||||
| Contractor's Profit | 10% | 0.1 | 7430 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2600.5 | |||||
| Total | 84330.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 6837.6 | ||||
| Grand Total | 91168.1 | |||||||
| Rate per kg | 91.17 | |||||||
| Rate per per kg | 91.17 | |||||||