Considering 1000 kg of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Grade 400/420(400Mpa / 400N/mm2 ≈ 60900psi/ 60 Grade), BDS-6935-2006, B400: and ratio fy to fu => 1.25 M.S. rod: 420 grade in/c 1% wastage | 1010 | kg | 72000 | per M. ton | 72 | 72720 | |
| 2 | G.I. wire G.I. wire | 10 | kg | 120 | per kg | 120 | 1200 | |
| 3 | Rod binder Rod binder | 2 | no | 700 | per day | 700 | 1400 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to rod binder | 9 | no | 550 | per day | 550 | 4950 | |
| 5 | Ordinary labour Local carriage, T & P etc. | 1 | LS | 550 | per day | 1100 | 1100 | |
| Sub-Total | 81370 | |||||||
| Contractor's Profit | 10% | 0.1 | 8137 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2847.95 | |||||
| Total | 92354.95 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 7488.23 | ||||
| Grand Total | 99843.18 | |||||||
| Rate per kg | 99.84 | |||||||
| Rate per per kg | 99.84 | |||||||