Considering one labour shed (12'X36')
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Erect and maintain labor shed with facilities in/c providing breast feeding zone, 3 nos ceinling fan, 06 nos energy saving lamp, 03 nos powerpoint and floor with sand filling & ramming up to desired compaction, BFS, Plaster with NCF.(Less salvage value) | LS | 115000 | |||||
| 2 | Remove labour shed (less salvage value) | LS | 12000 | |||||
| Sub-Total | 127000 | |||||||
| Contractor's Profit | 10% | 0.1 | 12700 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 4445 | |||||
| Total | 144145 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 11687.42 | ||||
| Grand Total | 155832.42 | |||||||
| Rate per each | 155832 | |||||||
| Rate per each | 155832 | |||||||