Break-up for 20 rft work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Aluminium sheet 16 BWG Aluminium sheet (1 x 20'-0" x 10" = 16.6 sft + Wastage 5% = 0.83 sft) = 17.43 sft = 3.77 kg | 3.77 | kg | 405 | Kg. | 405 | 1526.85 | |
| 2 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 3 | Skilled labour Skilled Labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 4 | Nails and wires G.I. Wire, nails etc. | 1 | LS | 70 | per kg | 29.17 | 29.17 | |
| 5 | Ordinary labour Tools and plants, sundries etc. | 1 | LS | 550 | per day | 45.83 | 45.83 | |
| Sub-Total | 2076.85 | |||||||
| Contractor's Profit | 10% | 0.1 | 207.69 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 72.69 | |||||
| Total | 2357.23 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 191.13 | ||||
| Grand Total | 2548.36 | |||||||
| Rate per rft | 127.4 | |||||||
| Rate per per rm | 418 | |||||||