Breakup

08.6 Supplying, fitting and fixing 250 mm wide 16 SWG Steel Sheet water stopper in RCC construction joint holding in position and keeping the water stopper in true horizontal or vertical by appropriate means as where necessary etc; all complete and accepted by the Engineer-in-charge.

Break-up for 20 rft work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Aluminium sheet 16 BWG Aluminium sheet (1 x 20'-0" x 10" = 16.6 sft + Wastage 5% = 0.83 sft) = 17.43 sft = 3.77 kg 3.77 kg 405 Kg. 405 1526.85
2 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
3 Skilled labour Skilled Labour 0.5 no 600 per day 600 300
4 Nails and wires G.I. Wire, nails etc. 1 LS 70 per kg 29.17 29.17
5 Ordinary labour Tools and plants, sundries etc. 1 LS 550 per day 45.83 45.83
Sub-Total 2076.85
Contractor's Profit 10% 0.1 207.69
Contractor's Overhead Expenses 3.5% 0.035 72.69
Total 2357.23
Add VAT with adjustment factor. 1.08108 7.5% 0.075 191.13
Grand Total 2548.36
Rate per rft 127.4
Rate per per rm 418