Breakup

01.25 Providing of dust preventive measures by regular watering the site at materials required and also supplying and laying of hessian cloth/ polythene sheet or tripol to cover construction materials including manpower support (payments will be made only one time based on the available area for construction material stackyard). All complete & accepted by the Engineer-in-charge.

Providing of dust preventive measures by regular watering the site and materials as required Considering 300 sft of covered area

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Jute hessian (for making formwork water-tight) Assuming 1 no of Hessian cloth of 20'-0" x 15'-0" size to cover 300 sft Cost of Hessian Cloth or Polythene sheet or tripol including labour cost for covering & watering materials 300 sft 3 per sft 3 900
2 Ordinary labour Ordinary labour 1 nos 550 per day 550 550
Sub-Total 1450
Contractor's Profit 10% 0.1 145
Contractor's Overhead Expenses 3.5% 0.035 50.75
Total 1645.75
Add VAT with adjustment factor. 1.08108 7.5% 0.075 133.44
Grand Total 1779.19
Rate per sft 5.93
Rate per sqm 63.83