Breakup

09.1.3 500 mm dia

Considering executing 500 mm dia & 20 meter long 0.95 No pile in a day.

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of cast in situ pile boring complete rig set including operational expenses Hire charge of rig set in/c fuel, lubricant, mobilization, demobilization, maintenance and insurance coverage etc. 1 day 8500 per day 8500 8500
2 Foreman/Supervisor Foreman/supervisor 1 no 850 per day 850 850
3 Skilled labour Skilled labour 3 nos 600 per day 600 1800
4 Ordinary labour Ordinary labour 6 nos 550 per day 550 3300
5 Bentonite Bentonite 30 kg/cum 36 per kg 134.06 4021.8
6 Ordinary labour power ,water, clean & sundry 1 LS 550 per day 429.69 429.69
Sub-Total 18901.49
Contractor's Profit 10% 0.1 1890.15
Contractor's Overhead Expenses 3.5% 0.035 661.55
Total 21453.19
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1739.45
Grand Total 23192.64
Rate per meter 1220.68
Rate per per meter 1220.68
Help