Considering executing 500 mm dia & 20 meter long 0.95 No pile in a day.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hire charge of cast in situ pile boring complete rig set including operational expenses Hire charge of rig set in/c fuel, lubricant, mobilization, demobilization, maintenance and insurance coverage etc. | 1 | day | 8500 | per day | 8500 | 8500 | |
| 2 | Foreman/Supervisor Foreman/supervisor | 1 | no | 850 | per day | 850 | 850 | |
| 3 | Skilled labour Skilled labour | 3 | nos | 600 | per day | 600 | 1800 | |
| 4 | Ordinary labour Ordinary labour | 6 | nos | 550 | per day | 550 | 3300 | |
| 5 | Bentonite Bentonite | 30 | kg/cum | 36 | per kg | 134.06 | 4021.8 | |
| 6 | Ordinary labour power ,water, clean & sundry | 1 | LS | 550 | per day | 429.69 | 429.69 | |
| Sub-Total | 18901.49 | |||||||
| Contractor's Profit | 10% | 0.1 | 1890.15 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 661.55 | |||||
| Total | 21453.19 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1739.45 | ||||
| Grand Total | 23192.64 | |||||||
| Rate per meter | 1220.68 | |||||||
| Rate per per meter | 1220.68 | |||||||