Breakup

09.3 Removing of spoils / mud accumulated during boring for cast in situ pile by wash boring from working site to a safe distance by contractor’s own arrangement i.e. with container set in truck or on cart including loading, unloading everything complete as per standard practice and accepted by the Engineer-in-charge. (Quantity should be given three times of solid volume of boring)

Considering 200cft of spoils/ mud removing work.

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hire charge of 3HP mud pump Hire charge of 3HP mud pump 0.25 day 645 per day 645 161.25
2 Hire charge of MS steel tank (6'-6" x 10'-0" x 4'-0") Hire charge of MS steel tank (6'-6" x 10'-0" x 4'-0") 1 trip 350 per trip 350 350
3 5-ton capacity truck-fare including loading & unloading (within 30 km radius) Hire charge of truck 1 trip 2300 per trip 2300 2300
4 Machine operator Pump operator 0.25 no 700 per day 700 175
5 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
6 Ordinary labour Sundries and incidental cost 1 LS 550 per day 171.88 171.88
Sub-Total 3433.13
Contractor's Profit 10% 0.1 343.31
Contractor's Overhead Expenses 3.5% 0.035 120.16
Total 3896.6
Add VAT with adjustment factor. 1.08108 7.5% 0.075 315.94
Grand Total 4212.54
Rate per cft 21.07
Rate per per cum 744.09