Considering 1 point welding
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Point welding Cost of Welding charge | 1 | point | 3 | per point | 3 | 3 | |
| Sub-Total | 3 | |||||||
| Contractor's Profit | 10% | 0.1 | 0.3 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 0.11 | |||||
| Total | 3.41 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 0.28 | ||||
| Grand Total | 3.69 | |||||||
| Rate per point | 4 | |||||||
| Rate per per point | 4 | |||||||