Considering 1 cum of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 2 | nos | 600 | per day | 600 | 1200 | |
| 2 | Ordinary labour Ordinary labour | 3 | nos | 550 | per day | 550 | 1650 | |
| 3 | Ordinary labour Repairing of pile head in/c materials | 1 | LS | 550 | per day | 250 | 250 | |
| 4 | Ordinary labour Straightening and bending of pile bars,tools & plant, sundries etc. | 1 | LS | 550 | per day | 429.69 | 429.69 | |
| Sub-Total | 3529.69 | |||||||
| Contractor's Profit | 10% | 0.1 | 352.97 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 123.54 | |||||
| Total | 4006.2 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 324.83 | ||||
| Grand Total | 4331.03 | |||||||
| Rate per cum | 4331 | |||||||
| Rate per per cum | 4331 | |||||||