Breakup

09.7 Labour for breaking head of hardened cast in situ bored pile/pre-cast pile up to a required length by any means but without damaging the rest and removing the dismantled materials such as concrete to a safe distance including scraps and cleaning concrete from steel/M.S. rods, straightening and bending of pile bars, preparation and making platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, leveling and dressing the situ and clearing the bed etc. complete in all respect and accepted by the Engineer-in-charge. (Measurement will be given for the actual pile head volume to be broken)

Considering 1 cum of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 2 nos 600 per day 600 1200
2 Ordinary labour Ordinary labour 3 nos 550 per day 550 1650
3 Ordinary labour Repairing of pile head in/c materials 1 LS 550 per day 250 250
4 Ordinary labour Straightening and bending of pile bars,tools & plant, sundries etc. 1 LS 550 per day 429.69 429.69
Sub-Total 3529.69
Contractor's Profit 10% 0.1 352.97
Contractor's Overhead Expenses 3.5% 0.035 123.54
Total 4006.2
Add VAT with adjustment factor. 1.08108 7.5% 0.075 324.83
Grand Total 4331.03
Rate per cum 4331
Rate per per cum 4331
Help