Mobilization and demobilization of testing
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 5-ton capacity truck-fare including loading & unloading (within 30 km radius) equipment (5 tonne) by truck | 2 | trips | 2300 | per trip | 2300 | 4600 | |
| Sub-Total | 4600 | |||||||
| Contractor's Profit | 10% | 0.1 | 460 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 161 | |||||
| Total | 5221 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 423.32 | ||||
| Grand Total | 5644.32 | |||||||
| Rate per set per site | 5644 | |||||||
| Rate per set per site | 5644 | |||||||