Breakup

09.8.3.1 For first test at one site for one testing set

considering test no. 1

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Platform making Platform making: 1 tonne 275 per tonne 13750 13750
2 Foreman/Supervisor Foreman 2 nos 850 per day 850 1700
3 Skilled labour Skilled labour 6 nos 600 per day 600 3600
4 Ordinary labour Ordinary labour 10 nos 550 per day 550 5500
5 Hire charge of load testing devices including hydraulic fluid: up to 200 ton capacity Hire charge of load testing equipment (joist, jacks and other necessary devices in/c charges, hydraulic fluid etc.) 1 test 7000 per test 7000 7000
6 Empty gunny bags/ Polymer bag to fill sand for load test Cost of empty gunny bags (taking 2 times use) 911.45 bags 20 each 5 4557.25
7 Sand (F.M. 0.8) Cost of local sand as loading materials (taking 2 times use) 911 cft 1670 per % cft 8.35 7606.85
8 Filling and stitching gunny bags Labour for bag filling, stitching, loading & unloading: 1823 bags 12 per bag 12 21876
9 Load testing result sheet preparation Preparation of test result in standard form in triplicate 1 test 6500 per test 6500 6500
10 Ordinary labour Other incidental charge 1 LS 550 per day 1100 1100
Sub-Total 73190.1
Contractor's Profit 10% 0.1 7319.01
Contractor's Overhead Expenses 3.5% 0.035 2561.65
Total 83070.76
Add VAT with adjustment factor. 1.08108 7.5% 0.075 6735.46
Grand Total 89806.22
Rate per test 89806
Rate per test 89806