Considering 2000 sft plinth area
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Foreman/Supervisor Foreman | 1 | no | 850 | per day | 850 | 850 | |
| 2 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 3 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| 4 | Ordinary labour Tools and plant, spikes, nails, chalk-powder etc. | 1 | LS | 550 | per day | 687.5 | 687.5 | |
| Sub-Total | 3237.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 323.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 113.31 | |||||
| Total | 3674.56 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 297.94 | ||||
| Grand Total | 3972.5 | |||||||
| Rate per sft | 1.99 | |||||||
| Rate per sqm | 21.42 | |||||||