considering test no. 1
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | For 2nd & additional tests at same site for same testing set (considering 10% reduced cost for empty gunny bags, local sand as loading materials, labour for filling, stitching, loading and unloading etc. - | 1 | - | 134826.3 | Per test | 134826.3 | 134826.3 | |
| Sub-Total | 134826.3 | |||||||
| Contractor's Profit | 10% | 0.1 | 13482.63 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 4718.92 | |||||
| Total | 153027.85 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 12407.65 | ||||
| Grand Total | 165435.5 | |||||||
| Rate per test | 165436 | |||||||
| Rate per test | 165436 | |||||||