09.8.6.1 For first test at one site for one testing set

considering test no. 1

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Platform making Platform making: 1 tonne 275 per tonne 55000 55000
2 Foreman/Supervisor Foreman 2 nos 850 per day 850 1700
3 Skilled labour Skilled labour 7 nos 600 per day 600 4200
4 Ordinary labour Ordinary labour 14 nos 550 per day 550 7700
5 Hire charge of load testing devices including hydraulic fluid: up to 200 ton capacity Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) 1 test 7000 per test 7000 7000
6 Empty gunny bags/ Polymer bag to fill sand for load test Cost of empty gunny bags (taking 2 times use) 3646 bags 20 each 5 18230
7 Sand (F.M. 0.8) Cost of local sand as loading materials (taking 2 times use) 3646 cft 1670 per % cft 8.35 30444.1
8 Filling and stitching gunny bags Labour for bag filling, stitching, loading & unloading: 7291 bags 12 per bag 12 87492
9 Load testing result sheet preparation Preparation of result in standard form in triplicate 1 test 6500 per test 6500 6500
10 Ordinary labour Other incidental charges 1 LS 550 per day 1100 1100
Sub-Total 219366.1
Contractor's Profit 10% 0.1 21936.61
Contractor's Overhead Expenses 3.5% 0.035 7677.81
Total 248980.52
Add VAT with adjustment factor. 1.08108 7.5% 0.075 20187.59
Grand Total 269168.11
Rate per test 269168
Rate per test 269168