Breakup

02.1.2 Earthwork in excavation in foundation trenches up to 1.5 m depth and maximum 10 m lead: in soft clayey soil / loose sand / silt

Considering 1000 cft work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Ordinary labour 5 nos 550 per day 550 2750
2 Skilled labour Skilled labour 1 no 600 per day 600 600
3 Ordinary labour Tools and plant, protecting and maintaining trench dry 1 LS 550 per day 137.5 137.5
Sub-Total 3487.5
Contractor's Profit 10% 0.1 348.75
Contractor's Overhead Expenses 3.5% 0.035 122.06
Total 3958.31
Add VAT with adjustment factor. 1.08108 7.5% 0.075 320.94
Grand Total 4279.25
Rate per cft 4.28
Rate per cum 151.15