Breakup

09.8.8.1 For first test at one site for one testing set

considering test no. 1

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Platform making Platform making: 1 tonne 275 per tonne 82500 82500
2 Foreman/Supervisor Foreman 2 nos 850 per day 850 1700
3 Skilled labour Skilled labour 8 nos 600 per day 600 4800
4 Ordinary labour Ordinary labour 16 nos 550 per day 550 8800
5 Hire charge of pile load testing devices including hydraulic fluid: up to 400 ton capacity Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) 1 test 9000 per test 9000 9000
6 Empty gunny bags/ Polymer bag to fill sand for load test Cost of empty gunny bags (taking 2 times use) 5469 bags 20 each 5 27345
7 Sand (F.M. 0.8) Cost of local sand as loading materials (taking 2 times use) 5469 cft 1670 per % cft 8.35 45666.15
8 Filling and stitching gunny bags Labour for bag filling, stitching, loading & unloading: 10937 bags 12 per bag 12 131244
9 Load testing result sheet preparation Preparation of result in standard form in triplicate 1 test 6500 per test 6500 6500
10 Ordinary labour Other incidental charges 1 LS 550 per day 1100 1100
Sub-Total 318655.15
Contractor's Profit 10% 0.1 31865.52
Contractor's Overhead Expenses 3.5% 0.035 11152.93
Total 361673.6
Add VAT with adjustment factor. 1.08108 7.5% 0.075 29324.86
Grand Total 390998.46
Rate per test 390998
Rate per test 390998