Breakup

02.1.5 Earthwork in excavation in foundation trenches up to 1.5 m depth and maximum 10 m lead: in very soft / saturated / organic clayey soil / soil of semi-liquid state.

protecting and maintaining the trench: very soft / saturated / organic clayey soil/ soil of semi-liquid state Considering 1000 cft work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Ordinary labour 10 nos 550 per day 550 5500
2 Skilled labour Ordinary labour 3 nos 600 per day 600 1800
3 Ordinary labour Tools and plant, protecting and maintaining trench dry 1 nos 550 per day 458.33 458.33
Sub-Total 7758.33
Contractor's Profit 10% 0.1 775.83
Contractor's Overhead Expenses 3.5% 0.035 271.54
Total 8805.7
Add VAT with adjustment factor. 1.08108 7.5% 0.075 713.97
Grand Total 9519.67
Rate per cft 9.52
Rate per per cum 336.2