protecting and maintaining the trench: very soft / saturated / organic clayey soil/ soil of semi-liquid state Considering 1000 cft work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Ordinary labour | 10 | nos | 550 | per day | 550 | 5500 | |
| 2 | Skilled labour Ordinary labour | 3 | nos | 600 | per day | 600 | 1800 | |
| 3 | Ordinary labour Tools and plant, protecting and maintaining trench dry | 1 | nos | 550 | per day | 458.33 | 458.33 | |
| Sub-Total | 7758.33 | |||||||
| Contractor's Profit | 10% | 0.1 | 775.83 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 271.54 | |||||
| Total | 8805.7 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 713.97 | ||||
| Grand Total | 9519.67 | |||||||
| Rate per cft | 9.52 | |||||||
| Rate per per cum | 336.2 | |||||||